Formwork Cost 
Non-discounted retail pricing for: Wood forms, staked. Used with form release agent or oil. For slabs, sidewalks and structures not to exceed 6 inch thickness. Quantity includes typical waste overage, material for repair and local delivery.
134 square feet$62.37$68.79
Concrete Form Setup Labor, Basic 
Basic labor to set concrete formwork with favorable site conditions. Layout finished height and slope. Lightly grade and compact soil. Place and secure forms. Excavation, gravel base layer, compaction or hardscape demolition are optional and have not included. Input to calculator is surface area of form in contact with concrete. Includes planning, equipment and material acquisition, area preparation and protection, setup and cleanup.
134 square feet$62.37$68.79
Concrete Form Setup Job Supplies 
Cost of related materials and supplies typically required to set concrete formwork including: reinforcing materials and additives, isolation materials, cleaning and chemical release agents .
134 square feet$62.37$68.79
Concrete Form Setup Equipment Allowance
Job related costs of specialty equipment used for job quality and efficiency, including: Pneumatic framing nailer, 12" miter saw and 3 1/4" electric planer. Daily rental. Consumables extra.
134 square feet$62.37$68.79
Option: Slab Excavation
Excavate with hand tools to a uniform depth below final surface level - to a maximum depth of 8 inches. For sidewalks, slabs and driveways. Distribute excavation material on site.
134 square feet$62.37$68.79
 Unused Minimum Labor
Balance of 2 hr(s) minimum labor charge that can be applied to other tasks.
   
Totals - Cost To Set Concrete Formwork   
Average Cost per Square Foot  
  Pros   
 Edit, Print & Save this in Homewyse Lists
  Pros   
 Build job winning estimates quickly

In January 2024 the cost to Set Concrete Formwork starts at $3.76 - $4.59 per square foot*. Use our Cost Calculator for cost estimate examples customized to the location, size and options of your project.

To estimate costs for your project:

1. Set Project Zip Code Enter the Zip Code for the location where labor is hired and materials purchased.

2. Specify Project Size and Options Enter the number of "square feet" required for the project.

3. Re-calculate Click the "Update" button.


NOTE: *Input the total of the finished surface area AND the area of any openings enclosed by the finished area.



 


Unit Costs = Successful Projects

Homewyse uses the Unit Cost Method for up-to-date example estimates and custom estimates created with Homewyse Lists. The Unit Cost Method promotes clear communication, sets realistic expectations between the customer and service professional - and results in mutual trust, fair pricing and high customer satisfaction.


Cost to Set Concrete Formwork - Notes and General Information

This example estimate is for BASIC work performed in easily serviceable conditions by qualified trade professionals, using popular, IN STOCK products, materials and supplies commonly available at home improvement retailers. Your actual costs will vary due to the unique situation, requirements and choices of your project. Work not mentioned on this page, work with schedule difficulty, and work using master craftsman, premium materials, custom built products and project supervision will result in HIGHER COSTS!

This example estimate is for educational and illustrative purposes - it is NOT a substitute for written quotes from trade professionals. Homewyse strongly recommends that you contact reputable professionals for accurate assessments of work required and costs for your project - before making any decisions or commitments.

The cost estimate includes:

  • Costs for local material / equipment delivery to and service provider transportation to and from the job site.
  • Costs to prepare the worksite for Concrete Form Setup, including costs to protect existing structure(s), finishes, materials and components.
  • Labor planning and setup time, mobilization time, cleanup time and as appropriate, time needed to achieve minimum job hours agreed to before work begins.

The cost estimate does NOT include:

  • Labor upcharges associated with master/premium craftsmanship, expedited scheduling, local labor shortages, difficult or complex site conditions, excessive transit times, service provider pricing discretion and failure of customer to negotiate labor costs.
  • Costs for removing, relocating, repairing, or modifying existing framing, surfacing (including molding), HVAC, electrical, and plumbing systems - or bringing any systems into compliance with current building codes.
  • Costs for testing and remediation of hazardous materials (asbestos, lead, etc.).
  • General contractor overhead and markup for organizing and supervising the Concrete Form Setup. Add 13% to 22% to the total cost above if a general contractor will supervise this project.
  • Sales tax on materials and supplies.
  • Permit or inspection fees (or portion thereof) required by your local building department for your overall project.

References - Concrete Form Setup

Concrete Form Setup Budget Management

Concrete Form Setup Cost Infographic - critical areas of budget risk and savings

This infographic highlights decisions and site issues that can cause large cost variances in the typical Concrete Form Setup budget.


Hiring Local Professionals

How to hire a trustworthy pro contractor for your project

Our FREE hiring guide helps you hire wisely, get quality craftsmanship and understand fair pricing for your specific project.



Make Homewyse better

We're an involved community that values your input. So, let us know - did we meet your needs? how can we improve this site? Your comments and sharing are greatly appreciated!

  • Send your feedback or questions.
  • Save and share Homewyse on social media using the buttons below:

 




By using Homewyse.com you agree to the
Homewyse Privacy Policy and Terms of Service
Contact - About - Don't sell my information 
©2006-2013